Factbox-US offshore wind tasks going through inflation headwinds By Reuters

0
Factbox-US offshore wind tasks going through inflation headwinds By Reuters

[ad_1]

© Reuters. FILE PHOTO: U.S. President Joe Biden holds up a wind turbine measurement comparability chart whereas attending a gathering with governors, labor leaders, and personal firms launching the Federal-State Offshore Wind Implementation Partnership, on the White Home in W

(Reuters) – The U.S. has no large-scale industrial wind farms in operation immediately, however President Joe Biden’s administration goals to have 30 gigawatt (GW) put in by 2030 to assist decarbonize the facility sector and revitalize home manufacturing. The federal authorities has already authorized a number of large-scale tasks up to now, with the primary two – Winery Wind 1 and South Fork – anticipated to ship first energy by the top of this yr, and about just a few dozen tasks are in several phases of improvement. Some 27 energy offtake contracts totaling greater than 17 GW had been signed by the top of Could, in line with a U.S. Division of Vitality report printed on Aug. 24. Nevertheless, inflation, provide bottlenecks and better financing prices have eroded profitability of many tasks, forcing some to cancel the offtake agreements, whereas others are nonetheless searching for to renegotiate the phrases, the report mentioned.

Some builders instructed Reuters they have been additionally urgent officers to ease necessities for subsidies underneath the year-old Inflation Discount Act.

Whereas wind energy prices had fallen by about 50% since 2014, a latest business survey confirmed prices rose by 11%-20% over 2022, and in some instances by 30%, the report mentioned.

Levelized value of power (LCOE), which evaluate the overall lifetime value of constructing and operating a plant to lifetime output, stood at between $72 and $140 per megawatt hour (MWh) within the U.S., an evaluation by funding financial institution Lazard (NYSE:) confirmed in April.

That in contrast with $24 to $96 for utility-scale photo voltaic, $24 for onshore wind and $39 to $101 for mixed cycle fuel.

To check, in 2022, wholesale electrical energy costs averaged about $92 in New England, $90 in New York and $83 within the PJM West Hub, which runs from western Pennsylvania to Washington, D.C., in line with U.S. Vitality Info Administration (EIA) information.

One megawatt (MW) can energy about 1,000 U.S. houses however since wind is an intermittent useful resource – 1 MW of offshore wind can energy about 500 U.S. houses, in line with offshore wind builders.

The next is a listing of main U.S. offshore wind tasks:

VINEYARD WIND 1The 800-MW challenge off the coast of Martha’s Winery plans to begin operations by the top of this yr. When absolutely operational in 2024, it’s anticipated to produce sufficient clear power for 400,000 houses in New England. The challenge is owned by Avangrid (NYSE:), part of Spanish Iberdrola (OTC:), and Danish inexperienced power investor Copenhagen Infrastructure Companions (CIP).

SOUTH FORKDenmark’s Orsted (CSE:), the world’s largest offshore wind energy developer, is constructing the 132-MW challenge off Rhode Island and Massachusetts. It additionally goals to grow to be operational by the top of this yr, reaching full capability to energy 70,000 houses in 2024.

OCEAN WIND 1&2In January, Orsted grew to become the only real proprietor of the challenge off southern New Jersey by buying the remaining stake from Public Service Enterprise Group (NYSE:).

In June, the state’s legislators agreed to let Orsted to maintain any federal tax credit score advantages the challenge will get as a substitute of passing the advantages to prospects.

Orsted mentioned on Aug. 29 it deliberate to take the ultimate funding choice (FID) on the challenge’s first stage in the direction of the top of 2023 or in early 2024.

Pending FID, it now expects to fee Ocean Wind 1 in 2026. The challenge’s second stage, the 1,148-MW Ocean Wind 2, is predicted to begin industrial operations in 2029.

REVOLUTION WINDThe 704-MW challenge owned by Orsted and New England utility Eversource Vitality (NYSE:) is predicted to ship 400 MW energy to Rhode Island and 304 MW to Connecticut from 2025-2026.

Orsted mentioned on Aug. 29 it deliberate to take the FID on the challenge’s first stage in the direction of the top of 2023 or in early 2024.

In March, Orsted and Eversource proposed to construct a second stage, 884-MW Revolution Wind 2, in Rhode Island’s newest wind solicitation.

The state’s utility Rhode Island Vitality, nonetheless, determined in opposition to signing an influence buy contract with the challenge, citing too excessive prices for customers.

COASTAL VIRGINIA OFFSHORE WIND (CVOW)The two,600-MW challenge owned by U.S. utility Dominion Vitality (NYSE:) is scheduled to begin building off the coast of Virginia Seashore in 2024, pending the federal approval, and to be accomplished in late 2026. Dominion constructed the primary section of the challenge – a two-turbine, 12-MW pilot in 2020. SUNRISE WINDThe challenge’s first stage, the 924-MW Dawn Wind 1, was anticipated to begin operations in 2025-2026, however its proprietor Orsted warned in June that it will not be capable of make the ultimate funding choice until the worth agreed in 2019 is adjusted for inflation.

The New York’s power company NYSERDA mentioned assembly Orsted’s request would imply rising the strike worth by 27%, and the New York states regulator has but to rule on the request.

Orsted mentioned on Aug. 29 it deliberate to take the ultimate funding choice (FID) on the challenge in the direction of the top of 2023 or in early 2024.

EMPIRE WIND 1&2Two tasks owned by Norway’s Equinor and British oil main BP (NYSE:) south of Lengthy Island are additionally searching for to renegotiate the beforehand agreed strike worth to regulate it for inflation and different value will increase.

The house owners mentioned the changes have been wanted to take care of the present challenge schedule with the 816-MW Empire Wind 1 and 1,260-MW Empire Wind 2 aiming to begin operations in 2027-2028.

NYSERDA estimated that the request would translate to strike costs rising for the 2 tasks by 35% and 66% to $159.64 per MWh and $177.84, respectively.

BEACON WIND 1

Equinor and BP are additionally searching for to renegotiate the beforehand agreed settlement for supplying energy from their 1,230-MW Beacon Wind 1 challenge in east of Montauk Level.

NYSERDA estimated that the request would outcome within the strike worth rising by 62% to $190.82.

Beacon Wind 1 is predicted to begin operations in 2028-2029, delivering sufficient energy to about 600,000 houses. A second a part of the Beacon Wind lease space, Beacon Wind 2, is comparable in measurement to Beacon Wind 1 and shall be developed sooner or later. SOUTHCOAST WIND

The challenge off Massachusetts, beforehand often called Mayflower Wind, is owned by oil main Shell (LON:) and Ocean Winds, a three way partnership of French ENGIE and a renewable arm of Portuguese power group EDP.

The challenge, which was beforehand scheduled to ship first energy in 2027, is going through potential delays because the house owners have canceled the beforehand signed energy buy agreements blaming provide chain bottlenecks and rising financing prices.

They paid native utilities about $60 million to get out of contracts, however mentioned they deliberate to re-bid within the state’s subsequent offshore wind solicitation.

COMMONWEALTH WINDThe 1,232-MW challenge off Massachusetts, which was previously part of the bigger New England Wind challenge, can be going through potential delays. Its proprietor Avangrid, part of Spanish power firm Iberdrola, has agreed to pay about $48 million to native utilities to get out of its beforehand signed settlement. Avangrid, nonetheless, additionally mentioned it deliberate to re-bid within the subsequent offshore win solicitation to proceed the challenge.

PARK CITY WINDAvangrid owns the 800-MW challenge off the coast of Massachusetts, which was previously part of the bigger New England Wind challenge.

In July, Avangrid mentioned it was working to handle the financial viability of the beforehand signed energy buy settlement with regulators and electrical distribution firms.

The challenge plans to begin operations in 2025-2027.

ATLANTIC SHORES OFFSHORE WIND SOUTHThe three way partnership between Shell and French EDF (EPA:) is creating a big offshore wind park off New Jersey.

They plan to start setting up its first 1,510-MW capability stage in 2024 with the purpose to ship first energy in 2027.

In July, Atlantic Shores mentioned it was in contact with state officers about extra assist for the challenge, following the state’s choice to grant tax reduction for Orsted’s Ocean Wind 1 challenge.

MARWIN

Maryland’s first offshore wind challenge is predicted to begin operations in 2025-2026. The 270-MW challenge is owned by US Wind, a subsidiary of Italy’s Renexia SpA.

MOMENTUM WINDThe 808-MW challenge additionally owned by US Wind off Maryland can be anticipated to begin operations in 2026-2028, producing sufficient clear power to energy greater than 250,000 houses.

SKIPJACK 1&2The challenge off Maryland is owned by Orsted and consists of two components. The 120-MW Skipjack 1 challenge is predicted to begin delivering energy in 2026-2027, and the 846-MW Skipjack 2 challenge one yr later.